Work Profile Report [33W16]

करडा-शिकारू मोटर मार्ग का निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0दे0सं0 455(1)।।।-2/05 दि0 24-2-06

TS Amount (lakhs) : 29.4 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

29.40

Resanction Cost :

29.40

Tentative Cost :

29.40

Exp. Upto Last Fy :

10.78

For CFY 2024-2025

Remaining :

18.62

Demand :

3.40

Allotment :

3.53

Exp in CFY :

3.53

Total Up to Date Exp :

14.30

Unstarted Work

Sanction on : 18 years 10 months ago

24 Feb 2006

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

0 %

Tentative Completion date on : 3 months 5 days from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
1.5
1
0.000
1
0.000
0.000

Remark

view all

वर्तमान मंे कास्तकारांे का प्रतिकर भुगतान की कार्यवाही की जा रही है। -- as on 06-Oct-2023

Rating : 50

No Forest Case in The Work

Hindrance / Bottleneck : Other Reason

Assets :

Work not linked with IM

Bridges on The Basis of AI: