Work Profile Report [33W30]

fमयांगाड से कुनारा लुदराला मोटर मार्ग का fनर्माण कार्य, fक0मी0 13 से 17
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 764/111‘2‘/08-65 प्रा0आ0/07 दि0 24-3-08

TS Amount (lakhs) : 183.75 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

183.75

Resanction Cost :

183.75

Tentative Cost :

183.75

Exp. Upto Last Fy :

15.06

For CFY 2024-2025

Remaining :

168.69

Demand :

100.00

Allotment :

91.23

Exp in CFY :

69.50

Total Up to Date Exp :

84.56

Construction Started

Sanction on : 16 years 7 months ago

24 Mar 2008

Physical Progress:

At start of FY 2024-2025 :

20 %

Up to Date :

80 %

Tentative Completion date on : 4 months 1 week from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
5
5
1.000
4
4.000
1.500

Remark

view all

Cutting Work start -- as on 06-Mar-2024

Rating : 83

No Forest Case in The Work

Hindrance / Bottleneck : Other Reason

Assets :

Work not linked with IM

Bridges on The Basis of AI: