Work Profile Report [33W323]

आराकोट गमरी मोटर मार्ग से इशाली गाॅव तक लिंक मार्ग का प्रथम चरण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks

    Tenders

    Aggrements

    Project Activities

    alerts

    Documents

Administrative Approval Detail : fजलाfधकारी का पत्रांक 370-बी/fज0यो0 (वर्ष 2011-12) fदनांक 28-9-11

TS Amount (lakhs) : 3 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

3.00

Resanction Cost :

3.00

Tentative Cost :

3.00

Exp. Upto Last Fy :

0.00

For CFY 2024-2025

Remaining :

3.00

Demand :

3.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.00

Unstarted Work

Sanction on : 12 years 10 months ago

28 Sep 2011

Physical Progress:

At start of FY 2024-2025 :

80 %

Up to Date :

80 %

Tentative Completion date on : 7 months 2 weeks from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Jobs
1
1
0
1
1
0

Remark

view all

उक्त कार्य में ग्रामीणों द्वारा विवाद किया जा रहा है। -- as on 31-Jul-2020

Rating : 88

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: