Work Profile Report [33W323]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : fजलाfधकारी का पत्रांक 370-बी/fज0यो0 (वर्ष 2011-12) fदनांक 28-9-11
TS Amount (lakhs) : 3 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
3.00
Resanction Cost :
3.00
Tentative Cost :
3.00
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
3.00
Demand :
3.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Unstarted Work
Sanction on : 13 years 1 month ago
28 Sep 2011
Physical Progress:
At start of FY 2024-2025 :
80 %
Up to Date :
80 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
उक्त कार्य में ग्रामीणों द्वारा विवाद किया जा रहा है। -- as on 31-Jul-2020
Assets :
Work not linked with IM
Bridges on The Basis of AI: