Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
33W38 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0दंे0सं0 829/।।।-2/06 -62 (प्रा0आ0)/05 टी0सी0/1 एस0सी0पी0 दि0 28-3-06
TS Amount (lakhs) : 48.1 Lacs
Financial Detail
Sanction Cost : 112.00 Lacs
Resanction Cost : 112.00 Lacs
Exp. Upto Last Fy : 75.71 Lacs
For CFY 2024-2025
Remaining : 36.29 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 75.71 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 25 %
Sanction on :
18 years 1 month ago
28 Mar 2006
Tentative Completion date:
10 months 2 weeks from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: no issue
अधिशासी अभियंता कार्यालय पत्रांक 1351/वनभूमि दि0 02-08-2023 द्वारा उपवन संरक्षक टौंस वन प्रभाग पुरोला को अवगत कराया गया है कि प्रस्ताव की प्रति पूर्व में ही दि0 26-03-2019 द्वारा सम्बन्धित कार्यालय में जमा करा दी गयी है। -- as on 03-Nov-2023
Physical Peramenters