Work Profile Report [33W45]

उत्तरकाशी के पुरोला पोरा से रामा मार्ग का नव निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शासनादेश सं0 3318/111(2) /06- 09 (प्रा0आ0)/06 टी0सी0-1 दि0 12-12-06

TS Amount (lakhs) : 81.48 Lacs

Budget Financial Head : SCSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

81.48

Resanction Cost :

81.48

Tentative Cost :

81.48

Exp. Upto Last Fy :

17.67

For CFY 2024-2025

Remaining :

63.81

Demand :

63.81

Allotment :

53.86

Exp in CFY :

14.72

Total Up to Date Exp :

32.39

Construction Started

Sanction on : 18 years 1 week ago

12 Dec 2006

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

50 %

Tentative Completion date on : 3 months 5 days from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
3
1.975
0.000
1.975
1.980
1.000

Remark

view all

अपर प्रमुख वन संरक्षक देहरादून द्वारा 24-1-23 को एफ0आर0सी0एम0 की बैठक मंे निर्देशित किया गया है कि विषयगत मार्ग को वनभूमि से न लेजाकर अन्य भूमि से ले जाया जाय, जिसके अनुपालन में नया समरेखण जिसमें वनभूमि नहीं पड़ती है, पर मोटर मार्ग निर्माण का कार्य किया जा रहा है। 1.50 कि0मी0 लम्बाई में पहाड़ कटान का कार्य किया जा चुका है। शेष प्रगति पर है। -- as on 04-Nov-2024

Rating : 52

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand