Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 1.975 | 0.000 | 1.975 | 1.980 | 0.000 |
33W45 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 3318/111(2) /06- 09 (प्रा0आ0)/06 टी0सी0-1 दि0 12-12-06
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 81.48 Lacs
Resanction Cost : 81.48 Lacs
Exp. Upto Last Fy : 17.67 Lacs
For CFY 2024-2025
Remaining : 63.81 Lacs
Demand : 63.81 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 17.67 Lacs
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
17 years 4 months ago
12 Dec 2006
Tentative Completion date:
10 months 2 weeks from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: no issue
संयुक्त निरीक्षण तिथि निर्धारित किये जाने हेतु उपवन संरक्षक टौंस पुरोला को पत्र प्रेषित।संयुक्त निरीक्षण दिनांक 13.06.2023 को सम्पन्न किया जा चुका है।संयुक्त निरीक्षण आख्या प्राप्त नही हुई है। -- as on 25-Sep-2023
Physical Peramenters