Work Profile Report [33W45]

उत्तरकाशी के पुरोला पोरा से रामा मार्ग का नव निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

Administrative Approval Detail : शासनादेश सं0 3318/111(2) /06- 09 (प्रा0आ0)/06 टी0सी0-1 दि0 12-12-06

TS Amount (lakhs) : 81.48 Lacs

Budget Financial Head : SCSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

81.48

Resanction Cost :

81.48

Tentative Cost :

81.48

Exp. Upto Last Fy :

17.67

For CFY 2024-2025

Remaining :

63.81

Demand :

63.81

Allotment :

12.00

Exp in CFY :

0.00

Total Up to Date Exp :

17.67

Construction Started

Sanction on : 17 years 8 months ago

12 Dec 2006

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

25 %

Tentative Completion date on : 7 months 2 weeks from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
3
1.975
0.000
1.975
1.980
1.000

Remark

view all

कार्य प्रारम्भ है। -- as on 01-Jul-2024

Rating : 27

Forest Case Pending At : 01: Withdraw

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: