Work Profile Report [33W597]

जनपद उत्तरकाशी के विकास खण्ड पुरोला मंे कमलेश्वर मन्दिर मोटर मार्ग का नव निर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan

  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शासनादेश सं0 5927/।।।(2)/13-31(प्रा0आ0) /2013 दिनांक 22 नवम्बर 2013

TS Amount (lakhs) : 27.99 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

27.99

Resanction Cost :

27.99

Tentative Cost :

27.99

Exp. Upto Last Fy :

10.49

For CFY 2024-2025

Remaining :

17.50

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

10.49

Work deferred

Sanction on : 11 years 1 month ago

22 Nov 2013

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

0 %

Tentative Completion date on : 3 months 6 days from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
3
0
0
-

Remark

view all

इस कार्यालय के पत्रांक 2583/वनभूमि दिनांक 30-12-2023 द्वारा संयुक्त निरीक्षण आख्या /उपयुक्तता प्रमाण-पत्र हेतु उपवनसंरक्षक टौंस वन प्रभाग पुरोला को पत्र प्रेषित तथा कार्यालय मुख्य अभियंता क्षेत्रीय कार्यालय लो0नि0वि0,देहरादून के पत्रांक सं0 3935/06(34)याता0-स्तर-1(क्षे0का0)/2024 दिनांक 24.08.2024 के द्वारा निरस्तीकरण प्रस्ताव प्रमुख अभियंता एवं विभागाध्यक्ष लो0नि0वि0,देहरादून को प्रेषित। -- as on 01-Oct-2024

Rating : 39

Forest Case Pending At : 04: DFO

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI: