Work Profile Report [34W1001]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शासनादेश सं0 ई-फाइल 46119 लो0नि0वि0 अनुभाग-2 देहरादून दि0 23.03.2023
TS Amount (lakhs) : 468.59 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
468.59
Resanction Cost :
468.59
Tentative Cost :
468.59
Exp. Upto Last Fy :
159.00
For CFY 2024-2025
Remaining :
309.59
Demand :
200.00
Allotment :
140.00
Exp in CFY :
73.92
Total Up to Date Exp :
232.92
Construction Started
Sanction on : 1 year 8 months ago
23 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
40 %
Up to Date :
60 %
Tentative Completion date on : 6 months 1 week from now
31 May 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
G3 work in progress. -- as on 14-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand