Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
34W1014 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई फाईल संख्या- 38540.00 दिनांक 30.06.2023
TS Amount (lakhs) : 261.62 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
261.62
Resanction Cost :
261.62
Tentative Cost :
261.62
Exp. Upto Last Fy : 187.45
For CFY 2024-2025
Remaining : 74.17
Demand : 74.16
Allotment : 50.00
Exp in CFY : 37.00
Total Up to Date Exp : 224.45
Work completed
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 100 %
Sanction on :
1 year 2 weeks ago
30 Jun 2023
Tentative Completion date:
2 months 5 days from now
23 Sep 2024
Actual Completion Date:
3 weeks 2 days ago
24 Jun 2024
Remark
Bottelneck: no issue
work completed. -- as on 29-Jun-2024
Physical Peramenters