Work Profile Report : 34W1085
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शासनादेश ई-फाईल संख्या- 38540/02 लोक निर्माण अनुभाग-2 देहरादून दि0 10.03.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
329.71
Resanction Cost :
329.71
Tentative Cost :
329.71
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
329.61
Demand :
220.00
Allotment :
167.99
Exp in CFY :
167.99
Total Up to Date Exp :
168.09
Construction Started
Sanction on : 11 months 3 days ago
10 Mar 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
40 %
Tentative Completion date on : 4 months 4 days from now
18 Jun 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अनुबन्ध गठित। दिनांक 23.05.2025 को Contractor को Letter of Acceptance (LOA) जारी कर दिया गया है। स्कपर कार्य प्रगति पर। Work in progress. -- as on 28-Nov-2025