Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 12 | 9.5 | 9.5 | 0 |
34W14 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 830/111-2 /06-29 प्रा0आ0/07 दिनांक 24.03.08
TS Amount (lakhs) : 341.12 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
296.88
Resanction Cost :
296.88
Tentative Cost :
296.88
Exp. Upto Last Fy : 220.69
For CFY 2024-2025
Remaining : 76.19
Demand : 76.20
Allotment : 40.00
Exp in CFY : 38.14
Total Up to Date Exp : 258.82
Work completed
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 100 %
Sanction on :
16 years 3 months ago
24 Mar 2008
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 15: AIP Nodal
Bottelneck: no issue
work completed. -- as on 17-Jun-2024