Work Profile Report [34W68]

कुथनोर से हलना मोटर मार्ग का नाम शहीद सुभाष चन्द के मोटर मार्ग।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शासनादेश संख्या 2952/।।।(2)/16-59 (प्रा0आ0)/2005 टी0सी0-1 दिनांक 9.11.2016

TS Amount (lakhs) : 350.43 Lacs

Budget Financial Head : SCSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

94.80

Resanction Cost :

350.43

Tentative Cost :

350.43

Exp. Upto Last Fy :

195.31

For CFY 2024-2025

Remaining :

155.12

Demand :

100.00

Allotment :

54.42

Exp in CFY :

54.42

Total Up to Date Exp :

249.73

Construction Started

Sanction on : 8 years 1 month ago

09 Nov 2016

Physical Progress:

At start of FY 2024-2025 :

60 %

Up to Date :

80 %

Tentative Completion date on : 1 year 5 days from now

31 Dec 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
6
6
4.000
2
0.000
0.000

Remark

view all

Part 2 work completed. Land compensation distribution is remaining. -- as on 23-Dec-2024

Rating : 103

Forest Case Pending At : 18: Final Approval

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: