Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 6.15 | 6.15 | 0 |
34W726 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 673/।।।(2)/16-01 (एम0एल0ए0) /2016 दिनांक 4.3.2016
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
35.98
Resanction Cost :
35.98
Tentative Cost :
35.98
Exp. Upto Last Fy : 2.34
For CFY 2024-2025
Remaining : 33.64
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.34
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
8 years 4 months ago
04 Mar 2016
Tentative Completion date:
7 years 1 month ago
31 May 2017
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
alignment approved. -- as on 12-Aug-2023
Physical Peramenters