Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6.4 | 6.4 | 6.4 | 0 |
34W906 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 2954/।।।(2)/16-29 (प्रा0आ0)/2006 दिनांक 9.11.2016
TS Amount (lakhs) : 434.06 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
434.06
Resanction Cost :
449.95
Tentative Cost :
449.95
Exp. Upto Last Fy : 432.08
For CFY 2024-2025
Remaining : 17.87
Demand : 1.98
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 432.08
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
7 years 8 months ago
09 Nov 2016
Tentative Completion date:
1 year 3 months ago
23 Mar 2023
Actual Completion Date:
2 years 3 months ago
23 Mar 2022
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
6.4 km road work complete. -- as on 18-Dec-2023
Physical Peramenters