Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 0 | 0 | 0 |
34W915 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 957/।।।(2)/21-02(एम0एल0ए0)/2017 दिनांक 31.03.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 77.64 Lacs
Resanction Cost : 77.64 Lacs
Exp. Upto Last Fy : 2.09 Lacs
For CFY 2024-2025
Remaining : 75.55 Lacs
Demand : 5.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 2.09 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
3 years 1 month ago
31 Mar 2021
Tentative Completion date:
1 month 1 week ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 09: GOI
Bottelneck: no issue
संमरेखण अुनमोदित। वनभूमि प्रस्ताव गठित किया जा रहा है। -- as on 07-Jan-2023
Physical Peramenters