Work Profile Report [36W136]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश संख्या 5810/।।।(2)/10-18(प्रा.आ.)/2010 टी.सी.-।। दिनांक 20.9.2010
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
65.45
Resanction Cost :
65.45
Tentative Cost :
32.22
Saving
33.23
Exp. Upto Last Fy :
7.22
For CFY 2025-2026
Remaining :
58.23
Demand :
20.00
Allotment :
4.01
Exp in CFY :
4.01
Total Up to Date Exp :
11.23
Work deferred
Sanction on : 15 years 2 months ago
20 Sep 2010
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 1 year 3 months from now
31 Mar 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 33.23 has been recorded as expected cost of work reduced from 65.45 to 32.22 . -- as on 10-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: