Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 12 | 12 | 12 | 0 |
36W253 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 1843/।।।(2)/16-06 (एम॰एल॰ए॰)/2015 दिनांक 02 जून 2016
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 41.72 Lacs
Resanction Cost : 41.72 Lacs
Exp. Upto Last Fy : 0.89 Lacs
For CFY 2024-2025
Remaining : 40.83 Lacs
Demand : 1.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.89 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
7 years 11 months ago
02 Jun 2016
Tentative Completion date:
10 months 2 weeks from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 03: DM
Bottelneck: CA Land
क्षतिपूरक वृक्षारोपण हेतु भूमि उपलब्ध करवाने हेतु इस कार्यालय के पत्रांक 779/10एल॰ए॰ दिनांक 08.04.2024 द्वारा जिलाधिकारी, चमोली को पत्र प्रेषित किया गया है। -- as on 01-May-2024
Physical Peramenters