Work Profile Report [36W449]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शासन की ई-फाईल संख्या 49189 दिनांक 24.08.2023 द्वारा प्राप्त।
TS Amount (lakhs) : 138.59 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
138.59
Resanction Cost :
138.59
Tentative Cost :
138.59
Exp. Upto Last Fy :
28.20
For CFY 2024-2025
Remaining :
110.39
Demand :
110.39
Allotment :
100.39
Exp in CFY :
90.31
Total Up to Date Exp :
118.51
Construction Started
Sanction on : 1 year 4 months ago
24 Aug 2023
Physical Progress:
At start of FY 2024-2025 :
30 %
Up to Date :
100 %
Tentative Completion date on : 2 months 6 days ago
19 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्वों का भ्ुागतान शेष। -- as on 04-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: