Work Profile Report [36W488]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासन की ई-फाईल संख्या 52211 एवं कम्प्यूटर जनित संख्या 1/249979/2024 दिनांक 25.10.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
641.86
Resanction Cost :
641.86
Tentative Cost :
641.86
Exp. Upto Last Fy :
78.02
For CFY 2025-2026
Remaining :
563.84
Demand :
320.00
Allotment :
91.26
Exp in CFY :
86.75
Total Up to Date Exp :
164.77
Construction Started
Sanction on : 8 months 3 weeks ago
25 Oct 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
12 %
Tentative Completion date on : 11 months 3 weeks from now
09 Jul 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अतिरिक्त पहाड़ कटान एवं सोलिंग का कार्य प्रगति में। -- as on 01-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: