Work Profile Report : 36W489
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शासन की ई-फाईल संख्या 84259/06 एवं कम्प्यूटर जनित संख्या 1/295099/2025 दिनांक 05.05.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NandDevi Rajjat ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
659.98
Resanction Cost :
659.98
Tentative Cost :
659.98
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
659.98
Demand :
320.00
Allotment :
328.59
Exp in CFY :
199.42
Total Up to Date Exp :
199.42
Construction Started
Sanction on : 9 months 1 week ago
05 May 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
30 %
Tentative Completion date on : 6 months 1 week from now
26 Aug 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
दीवार निर्माण, स्कपर निर्माण का कार्य प्रगति में।क्रैश बैरियर का कार्य पूर्ण -- as on 02-Jan-2026