Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 22 | 15.62 | 0.000 | 15.62 | 0.000 | 0.000 |
37W12 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 793 (1)/।। (2) 09-04 (मु0म0घो0) /09 लो0नि0 अनु0-2 देहरादून दिनांक 2/3/09
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 808.50 Lacs
Resanction Cost : 808.50 Lacs
Exp. Upto Last Fy : 8.12 Lacs
For CFY 2024-2025
Remaining : 800.38 Lacs
Demand : 1.00 Lacs
Allotment : 0.50 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 8.12 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
15 years 2 months ago
02 Mar 2009
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 07: Nodal
Bottelneck: no issue
वर्तमान में वन भूमि प्रस्ताव नोडल स्तर पर लम्वित। -- as on 01-May-2024
Physical Peramenters