Work Profile Report [37W306]

मींग गधेरे से गढ़नी मोटर मार्ग का निर्माण कार्य। (द्वितीय चरण)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Nabard
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

Administrative Approval Detail : 789/।।।(2)/18-05 (एम0एल0ए0) /2017 टी0सी0 दिनांक 23/02/2018

TS Amount (lakhs) : 176.58 Lacs

Budget Financial Head : NABARD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

176.58

Resanction Cost :

176.58

Tentative Cost :

176.58

Exp. Upto Last Fy :

165.48

For CFY 2024-2025

Remaining :

11.10

Demand :

1.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

165.48

In Maintenance After Completion

Sanction on : 6 years 5 months ago

23 Feb 2018

Physical Progress:

At start of FY 2024-2025 :

100 %

Up to Date :

100 %

Tentative Completion date on : 4 months 2 weeks ago

31 Mar 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
2.5
2.5
2.500
0
0.000
0.000

Remark

view all

कार्य दिनांक 19.11.2021 से अनुरक्षण के अन्तर्गत है। -- as on 01-Mar-2024

Rating : 100

Forest Case Pending At : 21: Final

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: