Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2.000 | 0 | 0.000 | 0.000 |
37W307 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 789/।।।(2)/18-05 (एम0एल0ए0) /2017 टी0सी0 दिनांक 23/02/2018
TS Amount (lakhs) : 197.81 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
197.81
Resanction Cost :
197.81
Tentative Cost :
197.81
Exp. Upto Last Fy : 178.43
For CFY 2024-2025
Remaining : 19.38
Demand : 19.38
Allotment : 17.38
Exp in CFY : 0.00
Total Up to Date Exp : 178.43
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 100 %
Sanction on :
6 years 4 months ago
23 Feb 2018
Tentative Completion date:
2 months 2 weeks ago
30 Apr 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
कार्य पूर्ण। -- as on 08-May-2024
Physical Peramenters