Work Profile Report [37W334]

fवकासखण्ड देवाल के अन्तर्गत ग्राम पंचायत नलधूरा तक मोटर मार्ग का नव fनर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 1191/।।।(2)/19-05 (एम0एल0ए0)/2017 दिनांक 28/2/19

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

43.60

Resanction Cost :

43.60

Tentative Cost :

43.60

Exp. Upto Last Fy :

0.51

For CFY 2025-2026

Remaining :

43.09

Demand :

0.51

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.51

Alignment Approved

Sanction on : 6 years 10 months ago

28 Feb 2019

Physical Progress:

At start of FY 2025-2026 :

10 %

Up to Date :

10 %

Tentative Completion date on : 1 year 2 months from now

31 Mar 2027

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
4
4
4
-

Remark

view all

वन भूमि प्रस्ताव डी0एफ0ओ0 स्तर पर। -- as on 05-Jul-2025

Rating : 10

Forest Case Pending At : 07: Nodal

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI: