Work Profile Report [37W429]

विकासखण्ड देवाल के अन्तर्गत पदमल्ला कंजेरू से एरेठा तक मोटर सेतु व मोटर मार्ग का निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

  • Project Activities
  • alerts

    Documents

    Samples

Administrative Approval Detail : 6040 (1)/।।।(2)/21-05 एम0एल0ए0/2017 टी0सी0

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

88.36

Resanction Cost :

88.36

Tentative Cost :

88.36

Exp. Upto Last Fy :

2.49

For CFY 2025-2026

Remaining :

85.87

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

2.49

Work deferred

Sanction on : 4 years 2 weeks ago

15 Dec 2021

Physical Progress:

At start of FY 2025-2026 :

1 %

Up to Date :

0 %

Tentative Completion date on : 2 months 4 weeks from now

31 Mar 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
8
8
8
-
Bridge
1
1
1
-

Remark

view all

निरस्तीकरण प्रस्ताव गठित किया जाना है। -- as on 05-Jul-2025

Rating : 3

No Forest Case in The Work

Hindrance / Bottleneck : To Cancel

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© 2026 PWD Uttarakhand