Work Profile Report [37W438]

चोपता से डडुवागाढ़ तक मोटर मार्ग का निर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Nabard
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

Administrative Approval Detail : 3588(1)/।।।(2) 21-05 (एम0एल0ए0)2017

TS Amount (lakhs) : 44.96 Lacs

Budget Financial Head : NABARD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

44.96

Resanction Cost :

47.04

Tentative Cost :

47.04

Exp. Upto Last Fy :

46.57

For CFY 2024-2025

Remaining :

0.47

Demand :

0.05

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

46.57

In Maintenance After Completion

Sanction on : 2 years 11 months ago

10 Sep 2021

Physical Progress:

At start of FY 2024-2025 :

100 %

Up to Date :

100 %

Tentative Completion date on : 4 months 2 weeks ago

31 Mar 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
2
2
2.000
0
0.000
0.000

Remark

view all

कार्य दिनांक 11.12.2022 से अनुरक्षण के अन्तर्गत है। -- as on 01-Mar-2024

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand