Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 11.95 | 11.95 | 0.000 | 11.95 | 0.000 | 0.000 |
37W487 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : पत्र सं0- 895/07याता0-पी0एम0जी0एस0वाई0-नि0 ।।। दिनांक 16.05.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
208.86
Resanction Cost :
208.86
Tentative Cost :
208.86
Exp. Upto Last Fy : 38.20
For CFY 2024-2025
Remaining : 170.66
Demand : 170.66
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 38.20
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 40 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
3 months 1 week from now
31 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति में। -- as on 13-Dec-2023
Physical Peramenters