Work Profile Report [37W490]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : पत्र सं0- 895/07याता0-पी0एम0जी0एस0वाई0-नि0 ।।। दिनांक 16.05.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
345.46
Resanction Cost :
345.46
Tentative Cost :
345.46
Exp. Upto Last Fy :
0.57
For CFY 2024-2025
Remaining :
344.89
Demand :
250.00
Allotment :
113.89
Exp in CFY :
113.89
Total Up to Date Exp :
114.46
Construction Started
Sanction on : 1 year 7 months ago
16 May 2023
Physical Progress:
At start of FY 2024-2025 :
20 %
Up to Date :
40 %
Tentative Completion date on : 3 months 5 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पी0सी0 कार्य प्रगति में। -- as on 21-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: