Work Profile Report [37W491]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : पत्र सं0- 895/07याता0-पी0एम0जी0एस0वाई0-नि0 ।।। दिनांक 16.05.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
113.29
Resanction Cost :
113.29
Tentative Cost :
113.29
Exp. Upto Last Fy :
47.61
For CFY 2024-2025
Remaining :
65.68
Demand :
65.60
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
47.61
Construction Started
Sanction on : 1 year 6 months ago
16 May 2023
Physical Progress:
At start of FY 2024-2025 :
15 %
Up to Date :
90 %
Tentative Completion date on : 1 month 4 weeks ago
25 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति में। -- as on 20-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand