Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9 | 9 | 0.000 | 9 | 9.000 | 9.000 |
Jobs | 1 | 0 | 0 | 0 | 0 |
37W514 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई पत्रावली संख्या:- 48456 लोक निर्माण अनुभाग-2 देहरादून दिनांक 21.08.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
190.04
Resanction Cost :
190.04
Tentative Cost :
190.04
Exp. Upto Last Fy : 28.89
For CFY 2024-2025
Remaining : 161.15
Demand : 137.99
Allotment : 109.10
Exp in CFY : 109.10
Total Up to Date Exp : 137.99
Work completed
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 100 %
Sanction on :
10 months 3 weeks ago
21 Aug 2023
Tentative Completion date:
1 month 7 hours ago
17 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण, दायित्व शेष। -- as on 14-Jun-2024
Physical Peramenters