Work Profile Report [37W532]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई-पत्रावली संख्या-54129/05 लोक निर्माण अनुभाग-2 देहरादून दिनांक 29.01.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
410.05
Resanction Cost :
410.05
Tentative Cost :
410.05
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
410.05
Demand :
130.00
Allotment :
100.87
Exp in CFY :
100.87
Total Up to Date Exp :
100.87
Construction Started
Sanction on : 10 months 3 weeks ago
29 Jan 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
50 %
Tentative Completion date on : 5 months 1 week from now
06 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी1,जी2,जी3 का कार्य प्रगति में। -- as on 21-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: