Work Profile Report : 37W532
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : ई-पत्रावली संख्या-54129/05 लोक निर्माण अनुभाग-2 देहरादून दिनांक 29.01.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
410.05
Resanction Cost :
410.05
Tentative Cost :
410.05
Exp. Upto Last Fy :
173.74
For CFY 2025-2026
Remaining :
236.31
Demand :
193.24
Allotment :
195.66
Exp in CFY :
195.66
Total Up to Date Exp :
369.40
Work completed
Sanction on : 2 years 2 weeks ago
29 Jan 2024
Physical Progress:
At start of FY 2025-2026 :
60 %
Up to Date :
100 %
Tentative Completion date on : 1 month 2 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 30-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: