Work Profile

अटल आदर्श ग्राम योजना के अन्र्तगत चट्वापीपल - झिरकोटी मोटर मार्ग का निर्माण कि0मी0 0.00 से 5.00


Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI: Chtawapipal Suspension Bridge Over Alaknanda River

Administrative Approval Detail : 337/।।।(2)/09-43(प्रा0आ0)/09 दि0 12.3.10

TS Amount (lakhs) : 166.55 Lacs

Financial Detail

Sanction Cost : 183.75 Lacs

Resanction Cost : 183.75 Lacs

Exp. Upto Last Fy : 183.72 Lacs

For CFY 2024-2025

Remaining : 0.03 Lacs

Demand : 0.00 Lacs

Allotment : 0.00 Lacs

Exp in CFY : 0.03 Lacs

Total Up to Date Exp : 183.74 Lacs

Work completed

Physical Progress:

At start of FY 2024-2025 : 98 %

Up to Date : 98 %

Sanction on :
14 years 3 months ago
12 Mar 2010


Tentative Completion date:
8 months 4 weeks from now
31 Mar 2025


Actual Completion Date:
1 year 3 months ago
01 Apr 2023


Rating : 111

Remark

Forest Status 21: Final

Bottelneck: no issue


वन भूमि की विधिवत स्वी. शा.सं. एक्स-4-16/1(489)/2015 दिनांक 22.12.2016 द्वारा प्राप्त। मार्ग के संरेखण में ग्रामीणों द्वारा विवाद को समाप्त कर 2.00 कि0मी0 में पहाड़ कटान एवं पार्ट-।। का कार्य पूर्णं, दायित्वों का भुगतान शेष। वन भूमि पेकेज संख्या:- एफ.पी./यू.के./ रोड़/12421/2015 -- as on 31-Jan-2023

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 5 2 2 0
Currently only Bank Gaurantee information is avilable