Work Profile Report [38W282]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0:- 4305/।।।(2)/11-16 (मु0मं0घो0) / 2011 दिनांक 16.09.2011
TS Amount (lakhs) : 2.68 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
50.32
Resanction Cost :
50.32
Tentative Cost :
24.72
Saving
25.60
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
50.32
Demand :
10.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Survey work done
Sanction on : 14 years 2 months ago
16 Sep 2011
Physical Progress:
At start of FY 2025-2026 :
80 %
Up to Date :
60 %
Tentative Completion date on : 1 year 3 months from now
31 Mar 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 25.6 has been recorded as expected cost of work reduced from 50.32 to 24.72 . -- as on 07-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: