Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
38W448 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं.:- 2380/।।।(2)/16-06(एम0एल0ए0)/ 2015 दिनांक 31.08.2016
TS Amount (lakhs) : 6.64 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
86.00
Resanction Cost :
86.00
Tentative Cost :
86.00
Exp. Upto Last Fy : 0.74
For CFY 2024-2025
Remaining : 85.26
Demand : 0.05
Allotment : 0.05
Exp in CFY : 0.05
Total Up to Date Exp : 0.79
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
7 years 10 months ago
31 Aug 2016
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: no issue
fद0 22.02.2020 को मार्ग के संरेखण सहमfत बन गयी है। पुनः सर्वे कार्य पूर्ण कर लिया गया है। भू-वैज्ञानिक को निरीक्षण आख्या दि0 31.12.2021 को प्राप्त। संरेखण प्रस्ताव अधी अभि0 के प. 1611/572याता-07/2022 दि0 10.05.2022 द्वारा अनुमोदित। दिनांक 29.11.2022 को संयुक्त निरीक्षण किया गया है। वृक्षों की सूची दिनांक 30.01.2023 द्वारा प्राप्त। डिजिटल मैप तैयार किये जा रहे हैं। -- as on 30-Jun-2023
Physical Peramenters