Work Profile Report [38W619]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : CA/80/2022-IX-3-Civil Aviation Department (Computer No. 37777)/1(07)/2020 Dated 24-02-2023
TS Amount (lakhs) : 257.07 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
257.07
Resanction Cost :
257.07
Tentative Cost :
257.07
Exp. Upto Last Fy :
213.72
For CFY 2025-2026
Remaining :
43.35
Demand :
1.67
Allotment :
40.20
Exp in CFY :
40.20
Total Up to Date Exp :
253.92
Work completed
Sanction on : 2 years 9 months ago
24 Feb 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य दिनांक 14/02/2024 में पूर्ण। 83 प्रतिशत भुगतान हो चुका है। अंतिम देयक रू0 38.53 लाख का भुगतान हेतु कोषागार को प्रेषित किया जा रहा है। -- as on 02-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: