Work Profile Report [38W678]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शासनादेश सं0 4088/।।।(2)/2023 (प्रा0आ0)/2023 दि0 01/11/2023
TS Amount (lakhs) : 227.09 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
227.09
Resanction Cost :
227.09
Tentative Cost :
227.09
Exp. Upto Last Fy :
176.47
For CFY 2025-2026
Remaining :
50.62
Demand :
43.65
Allotment :
43.65
Exp in CFY :
40.53
Total Up to Date Exp :
217.00
Work completed
Sanction on : 1 year 6 months ago
01 Nov 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व अवशेष। -- as on 31-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand