Work Profile Report [38W70]

सोनला - मैखुरा मोटर मार्ग से कांचुला - गैन मोटर मार्ग कि0मी0 0.00 से 10.00
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0ः-3174/।।।-2/06-32 (प्रा0आ0)/06 दि0 27.11.2006

TS Amount (lakhs) : 168 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

168.00

Resanction Cost :

168.00

Tentative Cost :

168.00

Exp. Upto Last Fy :

152.90

For CFY 2024-2025

Remaining :

15.10

Demand :

15.00

Allotment :

15.07

Exp in CFY :

15.07

Total Up to Date Exp :

167.98

Construction Started

Sanction on : 18 years 4 weeks ago

27 Nov 2006

Physical Progress:

At start of FY 2024-2025 :

80 %

Up to Date :

80 %

Tentative Completion date on : 3 months 5 days from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
10
2.5
2.5
-

Remark

view all

अवशेष लम्बाई 3.70 किमी0 का द्वितीय चरण स्टेज-। का आगणन रू0 157.52 लाख का गठित कर मुख्य अभियन्ता के पत्रांक 6086/07 (24) याता-गौचर-पैड़ी/2022 दिनांक 18/10/2024 द्वारा शासन को पे्रषित। -- as on 30-Oct-2024

Rating : 103

Forest Case Pending At : 17: AIP Govt of India

Hindrance / Bottleneck : Sanction Required form Govt

Assets :

Work not linked with IM

Bridges on The Basis of AI: