Work Profile Report [38W729]

सड़क सुरक्षा मद के अन्तर्गत गौचर-सिदोली मोटर मार्ग (राज्य मार्ग सं0-95) पर अवशेष सुरक्षात्मक कार्य। (किमी0 20.31 से 22.284)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

  • Samples

Administrative Approval Detail : 7349/III-(2)/2024-01 (P.A.)/2023 E-file No. 56385

TS Amount (lakhs) : 100.53 Lacs

Budget Financial Head : सड़क सुरक्षा कार्य ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

100.54

Resanction Cost :

100.54

Tentative Cost :

100.54

Exp. Upto Last Fy :

0.00

For CFY 2025-2026

Remaining :

100.54

Demand :

66.38

Allotment :

60.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.00

Construction Started

Sanction on : 6 months 1 week ago

06 Nov 2024

Physical Progress:

At start of FY 2025-2026 :

1 %

Up to Date :

0 %

Tentative Completion date on :

Yet To Decide

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
1.974
1.974
1.974
-

Remark

view all

कार्य प्रगति में। -- as on 01-Mar-2025

Rating : 0

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand