Work Profile Report : 38W757
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : E file No. 89744/06 Dt. 06/08/2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NandDevi Rajjat ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
310.23
Resanction Cost :
310.23
Tentative Cost :
310.23
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
310.23
Demand :
150.00
Allotment :
124.10
Exp in CFY :
74.61
Total Up to Date Exp :
74.61
Construction Started
Sanction on : 6 months 6 days ago
06 Aug 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
5 %
Tentative Completion date on : 4 months 2 weeks from now
30 Jun 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
दीवार, स्कपर, नाली आदि का कार्य प्रगति में। -- as on 31-Dec-2025