Work Profile Report [39W1005]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष लो0नि0वि0 उत्तराखण्ड, देहरादून का पत्र संख्या 895/07याता-पीएमजीएसवाई -नि0-।।। दिनांक 16.05.2023
TS Amount (lakhs) : 91.3 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
91.30
Resanction Cost :
91.30
Tentative Cost :
91.30
Exp. Upto Last Fy :
72.03
For CFY 2024-2025
Remaining :
19.27
Demand :
19.27
Allotment :
10.00
Exp in CFY :
2.51
Total Up to Date Exp :
74.54
Work completed
Sanction on : 1 year 6 months ago
16 May 2023
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
7 नं0 सेतुआंे पर रंग-रोगन एवं सुरक्षात्मक का कार्य पर्ण। -- as on 31-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand