Work Profile Report [39W1017]

पाण्डवथली उछोला माणा मोटर मार्ग का डामीकरण कार्य
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

Administrative Approval Detail : जिला अर्थ एवं संख्याधिकारी रूद्रप्रयाग का पत्र संख्या 213/जि0यो0/2023 दिनांक 28.06.2023

TS Amount (lakhs) : 24 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

24.00

Resanction Cost :

24.00

Tentative Cost :

24.00

Exp. Upto Last Fy :

0.00

For CFY 2024-2025

Remaining :

24.00

Demand :

24.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.00

Work completed

Sanction on : 1 year 1 month ago

28 Jun 2023

Physical Progress:

At start of FY 2024-2025 :

50 %

Up to Date :

100 %

Tentative Completion date on : 7 months 2 weeks from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Jobs
1
1
0
1
1
1

Remark

view all

0.60 किमी0 में PC का कार्य पूर्ण। दायित्व शेष। -- as on 31-May-2024

Rating : 225

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand