Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.5 | 2.5 | 0.000 | 2.5 | 2.500 | 2.500 |
39W1024 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. ।/41204/2023 ई-फाइल सं0-50408 लोक निर्माण अनुभाग-2 दिनांक 27.07.2023
TS Amount (lakhs) : 216.39 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
216.56
Resanction Cost :
216.56
Tentative Cost :
216.56
Exp. Upto Last Fy : 29.19
For CFY 2024-2025
Remaining : 187.37
Demand : 187.00
Allotment : 57.79
Exp in CFY : 57.77
Total Up to Date Exp : 86.96
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 90 %
Sanction on :
11 months 2 weeks ago
27 Jul 2023
Tentative Completion date:
1 month 3 weeks from now
13 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
2.50 किमी0 में पीसी का कार्य पूर्ण। किमी0 1,2 व 3 में दीवार निर्माण, 8 नं0 स्कपर का निर्माण कार्य पूर्ण। पक्की नाली व पैरापिट का कार्य प्रगति में। -- as on 25-Jun-2024