Work Profile Report [39W1025]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा.सं. ।/41204/2023 ई-फाइल सं0-50408 लोक निर्माण अनुभाग-2 दिनांक 27.07.2023
TS Amount (lakhs) : 217.15 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
217.42
Resanction Cost :
217.42
Tentative Cost :
217.42
Exp. Upto Last Fy :
31.50
For CFY 2024-2025
Remaining :
185.92
Demand :
131.74
Allotment :
132.68
Exp in CFY :
132.67
Total Up to Date Exp :
164.16
Work completed
Sanction on : 1 year 3 months ago
27 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
25 %
Up to Date :
100 %
Tentative Completion date on : 3 weeks 5 days ago
28 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
3.25 किमी0 P.C. कार्य पूर्ण। -- as on 25-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: