Work Profile Report [39W1033]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा.सं. 1/64728/2023 ई-फाइल सं0-54684 लोक निर्माण अनुभाग-2 दिनांक 27.10.2023
TS Amount (lakhs) : 8.7 Lacs
Budget Financial Head : Bridges State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
8.70
Resanction Cost :
8.70
Tentative Cost :
8.70
Exp. Upto Last Fy :
0.08
For CFY 2024-2025
Remaining :
8.62
Demand :
1.50
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.08
Unstarted Work
Sanction on : 1 year 1 month ago
27 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
0 %
Tentative Completion date on : 3 months 5 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पीपीआर एवं टोपोग्राफिक सर्वे का कार्य पूर्ण। विस्तृत आगणन गठन का कार्य प्रगति में। -- as on 05-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand