Work Profile Report [39W104]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : शा.स. 2490/।।।-2/08-06 (प्रा0आ0)/07 दि. 25.07.08
TS Amount (lakhs) : 276.53 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
358.00
Resanction Cost :
358.00
Tentative Cost :
358.00
Exp. Upto Last Fy :
298.15
For CFY 2024-2025
Remaining :
59.85
Demand :
5.00
Allotment :
2.50
Exp in CFY :
0.00
Total Up to Date Exp :
298.15
Construction Started
Sanction on : 16 years 3 weeks ago
25 Jul 2008
Physical Progress:
At start of FY 2024-2025 :
80 %
Up to Date :
80 %
Tentative Completion date on : 7 months 2 weeks from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
मार्ग निर्माण कार्य पूर्ण। सेतु के डिजाइन हेतु कार्यवाही गतिमान। -- as on 14-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand