Work Profile Report [39W1053]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : शा0सं0 2451/।।।(2)/23-01(प्रा0आ0)/2019 दिनांक 21.07.2023
TS Amount (lakhs) : 924.35 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
924.35
Resanction Cost :
924.35
Tentative Cost :
924.35
Exp. Upto Last Fy :
921.61
For CFY 2024-2025
Remaining :
2.74
Demand :
2.74
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
921.61
Work completed
Sanction on : 1 year 4 months ago
21 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Crash Barrier Fixing work complete. -- as on 31-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: