Work Profile Report [39W1070]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 185624/2024 ई पत्रावली संख्या 48456 लोक निर्माण अनुभाग दिनांक 30.01.2024
TS Amount (lakhs) : 276.72 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
276.72
Resanction Cost :
276.72
Tentative Cost :
276.72
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
276.72
Demand :
276.72
Allotment :
205.00
Exp in CFY :
206.05
Total Up to Date Exp :
206.05
Construction Started
Sanction on : 9 months 4 weeks ago
30 Jan 2024
Physical Progress:
At start of FY 2024-2025 :
10 %
Up to Date :
80 %
Tentative Completion date on : 4 months 3 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
15.35 किमी0 में पीसी कार्य पूर्ण। शेष दीवार एवं नाली निर्माण का कार्य प्रगति में। -- as on 24-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: