Work Profile Report [39W1073]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा.सं. 1/1999982/2024 ई फाइल संख्या 51812 लोक निर्माण अनुभाग 02 दिनांक 16.03.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
82.46
Resanction Cost :
82.46
Tentative Cost :
82.46
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
82.36
Demand :
80.00
Allotment :
80.00
Exp in CFY :
58.67
Total Up to Date Exp :
58.77
Construction Started
Sanction on : 8 months 1 week ago
16 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
0 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति में। -- as on 05-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand