Work Profile Report [39W367]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 3698(1)/।।।(2)/12-04(मु0मं0घो0) /2012 दिनांक 18.10.2012
TS Amount (lakhs) : 3.05 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
63.00
Resanction Cost :
63.00
Tentative Cost :
63.00
Exp. Upto Last Fy :
1.36
For CFY 2024-2025
Remaining :
61.64
Demand :
0.10
Allotment :
1.38
Exp in CFY :
1.37
Total Up to Date Exp :
2.73
Unstarted Work
Sanction on : 12 years 2 months ago
18 Oct 2012
Physical Progress:
At start of FY 2024-2025 :
1 %
Up to Date :
1 %
Tentative Completion date on : 3 months 5 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सर्वे कार्य पूर्ण। ग्रामीणों से अनापत्ति प्राप्त की जा रही है। -- as on 31-Dec-2022