Work Profile Report [39W63]

उत्यासू-मल्यासू-बांसी मोटर मार्ग का निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा.सं. 764/।।।(2)/08-85 (प्रा0आ0)/07 दि. 24.03.08

TS Amount (lakhs) : 107.7 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

110.25

Resanction Cost :

110.25

Tentative Cost :

110.25

Exp. Upto Last Fy :

102.30

For CFY 2024-2025

Remaining :

7.95

Demand :

7.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

102.30

Construction Started

Sanction on : 16 years 9 months ago

24 Mar 2008

Physical Progress:

At start of FY 2024-2025 :

80 %

Up to Date :

80 %

Tentative Completion date on : 8 months 3 weeks ago

31 Mar 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
3
3
0.000
3
0.000
0.000

Remark

view all

भारत सरकार के पत्र संख्या 8बी/यूसीपी/06/91/2012/एफसी/2714 दिनांक 31.03.2016 द्वारा आॅफ लाइन (Offline) विधिवत स्वीकृति प्राप्त।
3.00 किमी0 में पहाड कटान कार्य पूर्ण। दायित्व शेष।
-- as on 26-Dec-2023

Rating : 93

Forest Case Pending At : 18: Final Approval

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand