Work Profile Report [39W699]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश संख्या 1326/।।।(2)/19-08 (एमएलए)/2017टीसी ।।। दिनांक 10.03.2019
TS Amount (lakhs) : 91.58 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
91.58
Resanction Cost :
91.58
Tentative Cost :
91.58
Exp. Upto Last Fy :
84.81
For CFY 2024-2025
Remaining :
6.77
Demand :
6.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
84.81
Work completed
Sanction on : 5 years 9 months ago
10 Mar 2019
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 8 months ago
31 Mar 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
2.00 किमी0 में पहाड कटान व दीवार निर्माण कार्य पूर्ण। दायित्व शेष। -- as on 21-Nov-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand